Concrete calculator

Concrete volume for a rectangular slab or base. Enter the sizes, waste allowance and the yield of a bag or ready-mix load.

Measurements
YOUR ESTIMATE
Enter measurements

Switch measurement systems without changing your project. US gallons and US fluid ounces are used for imperial liquid measurements. Enter current supplier prices per listed unit. Blank prices are not included. No live feed.

Compare supplier prices ↓
COMPARE & SAVE

Find a cheaper basket

Search suppliers or compare quotes for the quantities above. No automatic supplier feed is connected.

You can also type a barcode or product code in the search field above.

Search links open external Google results for your region; confirm exact product, pack size, availability and trade eligibility.

Compare supplier quotes

Optional: enter quoted prices per listed purchase unit. No owner-maintained price database is needed. Enter comparable unit prices; leave unavailable items blank. The smart basket compares split orders including delivery and applicable tax.

Build a job quote

Use the full entered material total or enter your own. Add labour, expenses and markup.

—

Before any additional sales tax or VAT. Use consistent tax basis for all costs. Markup is not profit margin.

Before you buy

Volume = length × width × depth, plus waste, rounded up using your bag or load yield. Excludes reinforcement, formwork, labour and structural design. Check the mix, slump and site access.

Quantity estimates only. Verify dimensions, manufacturer coverage, product suitability and local requirements. Not structural or installation advice.

How to measure for a concrete volume

This calculator is for a rectangular slab, path or base. Measure the length and width in metres, then enter the depth in millimetres. Depth should be the thickness of the concrete you intend to place, measured consistently — not a mix of finished level and excavation depth.

If the plan is made of more than one rectangle, run the calculator for each part and add the volumes. Do not use this page to choose a depth or to design a foundation. Enter the sizes for your project, then treat the result as a quantity estimate only.

Enter the yield of one bag or one ready-mix load, in cubic metres. That figure should come from the bag or the supplier. Add a waste allowance for spillage and uneven ground. Ten percent is only the example on this page; you can set it to zero or raise it. The result is a volume in cubic metres, or cubic yards if you switch to imperial, and a count of bags or loads rounded up.

Worked example

A rectangle is 5 m by 4 m and 100 mm deep. Waste is 10%. Each bag is entered as yielding 0.015 m³.

The raw volume is 5 × 4 × 0.1 = 2.0 m³. With 10% allowance that becomes 2.2 m³. Divided by 0.015 m³ per bag, that is 146.67, which rounds up to 147 bags. In imperial the same project is shown as 2.88 yd³. These are the default figures when you open this page. A 0.015 m³ yield is only an example — replace it with the yield on your bag or quote.

Common mistakes

Typical UK bag and load units

In the UK, bagged concrete and ballast mixes are commonly sold in 20 kg and 25 kg bags. The mixed volume from a bag is not the same as its weight, and it varies by product, so this calculator asks for yield in cubic metres rather than assuming a bag size. Ready-mixed concrete is usually ordered in cubic metres. There is no single standard yield that fits every bag, which is why the default 0.015 m³ must be checked against your product.

Frequently asked questions

How much concrete for a 5 m by 4 m area, 100 mm deep?

With 10% waste and a bag yield of 0.015 m³, this calculator gives 2.2 m³, which is 147 bags, or 2.88 cubic yards if you switch to imperial.

What does the yield figure mean?

It is the volume of mixed concrete you get from one bag, or from one ready-mix load, in cubic metres. Enter the yield from your supplier or bag, not a guess copied from another product.

Can I use this for a path or pad that is not a rectangle?

Split the shape into rectangles, calculate each one, and add the volumes. This tool does not design foundations or set a depth for you.

Does the waste allowance change the bag count?

Yes. Volume is increased by the waste percentage before it is divided by the yield and rounded up to whole bags or loads.